[Bordermarch] Individual Monthly Report for July, 2007
Lathrop, Dave
Dave.Lathrop at valero.com
Mon Jul 30 05:36:01 PDT 2007
ACTIVITIES REPORT for July, 2007
for
Dave Lathrop
Current Month Activities
1. Check contractor electrical and instrument drawing packages
during approval and construction cycles:
DCU-843 Top Sludge Injection (Phase 2)
2. Design Installation Details for LT-8205
2. Review Evergreen Area Classification Drawings.
3. Review Radio system Grounding Drawings
4. Review Area Classification for Location at Fire Station/Medical
Change House/ Southside Central Control Room
5. Review Area Classification for SRTF Knock Engine Lab
Next Month Planned Activities
1. Revising drawings and close out assorted MOC packages
2. Update overall plant fiber optic drawings to include fiber
optic routing.
3. Check contractor electrical and instrument drawing packages
during approval and construction cycles: