Angus, Morgan and I went out to the scout camp on Saturday. We selected the 
location of the fort and used marker flags to lay out a rough location of the 
main gate and the walls. The next step is to set the poles. This coming Saturday 
looks to be a good time to do this. At this time the weather forecast has it 
sunny with the temperature in the mid to low 50s. We may need some folks willing 
to do some hauling to get the materials to site. The heaviest part will be the 
37 bags of Quikcrete at 80#/bag. We will use machinery to dig the post holes, 
but there will be a potential need to bust up some rocks. Other than that there 
will be a need for hands to do some totin' and fetchin'.

So, who is willing to help with this?